Skip to content

Port Waikato erosion

20 December 2024 - Application for temporary seawall

Timeline and next steps

Late August 2024:   Initial idea of a proposed temporary wall structure raised by Sunset Beach Surf Lifesaving Charitable Trust, which was to be located adjacent to the Surf Lifesaving building only. This initial concept extended approximately 80 metres. 

6 November 2024:   Sunset Beach Surf Lifesaving Charitable Trust lodged a resource consent application with the Waikato District Council for a sea wall approximately 380 metres in length, located on both Waikato District Council owned and private properties on the seaward side of Ocean View Road.  

Port Waikato proposed temporary sea wall map

 
The proposal includes the installation of wooden poles up to 4.0 meters in length, 3.0 meters into the sand, with 150mm gaps.  This would then be backfilled with a mixture of natural materials like sand, rocks and wood. 

Mid-November:  Council worked with the applicant to clarify a number of aspects of the application so that it could continue to be processed.  

5 December 2024:  On reviewing the application, Council determined that the application needed to be peer reviewed by a technical expert to clarify the effects it may have on the environment, as per Section 92(2) of the Resource Management Act 1991 (the RMA). 

12 December 2024:  Applicant agreed to the commissioning of the report. 

Status as at 20 December 2024: The application is currently on hold until the above report is received by Council, at which point processing and assessment of the application under the RMA will resume. 

Next steps 

  • Once the report is received by Council (expected early February), a decision will be made by Council if any further information is required from the Applicant under Section 92(1) of the RMA. 
  • Once all information is received, Council will undertake a formal assessment of affected parties and make a decision as to whether the application will be processed on a non-notified, limited notified or fully notified basis under Section 95 of the RMA.     
  • If the Council considers that the adverse effects of the proposal on the environment beyond the adjacent properties are likely to be more than minor, the application must be publicly notified.  
  • A publicly notified application is advertised in the local newspapers and the Council also informs the affected neighbours. Anyone can lodge submissions supporting or opposing the application, which would extend the application process. 

29 November 2024 update

Car park and hub 

Council will be doing some further maintenance in front of the hub as we lead into summer, including a tidy-up of the safety works. Thanks to the resilience group for helping us work through these priorities, and to The Port Project for their support and delivery of some of the planned work.  

  • An additional metre of car park will be scraped back in the next few weeks, to leave an asphalt pathway along the hub frontage and uniform edge to reduce the risk of overhang  
  • We've moved the bins back to a safer position and less intrusive position on the reserve  
  • We’re about to remove the old light pole that is no longer working 
  • The sandbagging will be removed soon as there is far less area generating overland flow and run off to the dune now  
  • The Port Project will be kindly providing a load of marine rope donated during their recent careers day, which will be used along with some recycled bollarding to make a stronger temporary barrier 
  • Regular seasonal maintenance to the accessway is also due to ensure its in top condition for the summer period 

The team is having regular discussions with members of the Sunset Beach Surf Lifesaving Trust around activity for summer and future operational plans for the site.  

  • On advice from a specialist house-moving company and our own regulatory team, we are monitoring safe distances for contingencies relating to the hub if needed.   
  • Council has allowed some flexibility for the board riders shack to be put in place on condition that they go through the usual processes retrospectively. 
  • The surf lifesaving tower is easily relocatable if necessary.

    Meet Steph from parks and reserves   

    Stephanie Loughnan is the Team Leader in our Open Spaces team and is now our head person for operational reserve space works for Port Waikato. Steph has worked in Glyn Morgan’s team at Waikato District Council for 3 years and is already a familiar face to many of you. Feel free to stop and say Hi next time she’s out on site.  

    Stephanie Loughnan

    Sunset Beach, natural solutions wall 

    Waikato District Council has received the resource consent, and it is being processed in-house.   

    Stormwater upgrades

    Stay up-to-date on the Port Waikato resilience project

    Learn more

     
    Recent updates


    Upcoming community meetings

    No events found.


    Stay informed

    Subscribe to our Port Waikato newsletter.

    Subscribe now

    Download the Antenno app

    Use the Antenno app to tell us about things that need our attention, like potholes, graffiti, or broken streetlights.

    More about Antenno

    Top